REVISED VEHICLE SIZE RESTRICTIONS, STARTING JULY 14, 2025
The following vehicle size restrictions will be in place starting July 14, 2025, for a period of two weeks.
|
Highway 27 Construction Update- July 24 We’re almost there! Crews are making great progress across
all areas of the project, and if the weather holds, Highway 27 is expected to
re-open to two-way traffic next week! Thank you for continuing to drive
carefully and for your patience through the busy summer construction season.
Progress to date:
What’s coming in the next two weeks:
Thanks again for your continued patience as crews work hard to wrap up the rest of the work over the next few weeks. |
Highway 27 Construction Update – July 18
We’re in the home stretch! Crews are making great progress across the corridor — with concrete work, paving, and landscaping nearly wrapped up. Thank you for your continued patience as we move into the final stages of this project. Progress to date: · Bridge area: Curb removal on the northeast side is now complete, and the northwest side has been excavated, graded, and prepared for new curb and asphalt. · 2nd Street (north side): All grey and coloured concrete has been placed, and the area is now ready for the final patterned concrete pour; the first two lifts of asphalt are complete. · 2nd Street (south side): Landscaping and installation of the signage and railing are complete. · 4th Street (north side): All concrete is poured, including patterned sections; the second lift of asphalt has also been placed. What’s coming in the next two weeks: · Bridge area: On the northwest side, curb and gutter will be graded and formed in the next couple of days, followed by concrete pouring and asphalt paving soon after; a new steel barrier will be installed early next week while the bridge remains open with flaggers in place to help keep traffic flowing. On the northeast corner, curb and gutter work is expected to be completed next week, followed by installation of the new steel barrier. The bridge is expected to open to two way traffic on July 22, weather permitting. · 2nd Street (north side): Final patterned concrete is expected to be poured this weekend. · 3rd Street (north side): Signage installation is underway and will continue through the week. · 3rd Street (south side): Landscaping, coloured concrete work, and sign installation are expected to begin within the next few days. · 4th Street (north side): Landscaping and final signage installation are planned for this week. · 4th Street (south side): Crews will begin installing signs, boulders, and bollards over the coming days. · Highway 27: The final lift of asphalt is scheduled to be placed on the north side between 1st and 4th Streets by the end of the week, with paving of the remaining sections continuing into next week. Line painting will begin early next week on the north side and carry through to the rest of the highway by the end of the month. Crews are aiming to open Highway 27 to two-way traffic on August 1, weather dependent. 🚨 Reminder: Temporary Vehicle Size Restrictions in Effect Temporary size restrictions are currently in place through the project area:
While some work is still ongoing, much of the heavy lifting is done and crews are shifting their focus to finishing touches. Thank you again for your continued patience — we’re almost there! |
Project Overview
Detour Route & Vehicle Size Restrictions
REVISED VEHICLE SIZE RESTRICTIONS, STARTING JULY 14, 2025
The following vehicle size restrictions will be in place starting July 14, 2025, for a period of two weeks.
|
Project Background
Highway 27 plays a key role in supporting the growth and development of several central Alberta communities. Within the Town of Sundre, Highway 27 is designated as an Over Sized Over Weight (OSOW) route and is a key contributor to Alberta’s High Load Corridor.
Alberta Transportation and Economic Corridors (TEC) has planned improvements to Highway 27 through the Town of Sundre, from the east boundary of the Town to the west boundary. The improvements are designed to support safer, more efficient travel through this area and enhance pedestrian safety.
The planned improvements include:
· Single lane roundabout at Highway 27/22/584/Range Road 54 (10th Street) intersection
· Permanent mini roundabouts at 2, 3 and 4 Street (West) intersections
· Intersection improvements at 1 Street (West) (right-in, right-out)
· Pavement rehabilitation, improvements to curbs, gutters, sidewalks, access management and lighting.
Following public engagement in 2022, additional improvements were identified including intersection upgrades at Centre Street, the Red Deer River bridge approach slabs, signalization of Highway 760 intersection, waterline relocations and additional lighting improvements.
The temporary mini roundabouts installed as a pilot project in 2017 have been assessed and deemed effective in improving both traffic flow as well as pedestrian safety. As such, TEC have directed the installation of permanent roundabouts along Highway 27 at 2 Street, 3 Street and 4 Street in 2024.
The anticipated timeline for the TEC improvements to Highway 27 is as follows:
- 2025 (January to February) - Miscellaneous construction activities (e.g. utility relocation, clearing of construction laydown area – in the northeast quadrant of Hwy 27/22/584/10th Street Intersection
- 2025 (March to October) – Construction activities for Hwy 27 Improvements
- 2025 (November) – Hwy 27 Construction completion (contingent on weather)
For more information about the Highway 27 improvement project, visit Highway 27 Improvements (Sundre) | Alberta.ca
Contact Information
If you have questions about this year’s construction work, please contact hwy27@sundre.com.
If you are interested in receiving project updates, please fill out the form below: