REVISED VEHICLE SIZE RESTRICTIONS, STARTING JUNE 2, 2025
The following vehicle size restrictions will be in place starting June 2, 2025, for a period of three weeks.
|
|
Highway 27 Construction Update – May 12
Crews have been making steady progress as visible
improvements continue along Highway 27. Thanks to everyone for your patience as
we work through the busy spring construction season.
Please note: Milling and paving work originally
scheduled for overnight will now take place during the day, with early morning
starts. While work will begin as early as 4:00 a.m. on some days, all work will
be completed during daytime hours. We appreciate your understanding around the
additional noise and traffic impacts as we work to complete these upgrades as
quickly as possible.
Progress to date:
· 1st Street: Concrete and asphalt have been
removed and grading for sidewalks and bump-outs is underway.
· 2nd Street: Stamped and coloured concrete has been poured; asphalt tie-ins are complete, and landscaping is underway.
· 4th Street: Mini-roundabout, sidewalks, and
curbs have been poured on the south side; asphalt placement has started.
· Centre Street: Sidewalks and curbs are poured;
removals of old barriers and grading for parking lot connections is ongoing.
·
1st Street: Grading continues ahead of concrete
pours for sidewalks, aprons, and bump-outs.
·
2nd Street: Final stamped concrete pours, sign
installation, and remaining landscaping, including handrail installation near
Burger Baron.
·
3rd Street: Asphalt paving, sign installation,
and asphalt tie-ins will wrap up the north side; removals and road grading will
begin on the south side.
·
4th Street: Final concrete pour for the
roundabout’s inner circle, streetlight pole installation, and asphalt tie-ins
for nearby parking lots.
·
Centre Street: Asphalt will be placed in the
turning lane and parking lot tie-ins; prep work begins for removals in June.
·
Highway 27 milling and paving work:
·
Milling: May 14–15 (early morning starts, 4–5
a.m.)
·
Paving: May 21–25 (early morning starts, 5–6
a.m.)
·
Line Painting: May 24–27 (daytime hours)
Traffic Pattern Shift – May 21
A reminder that new traffic patterns will go into effect on
May 21, with traffic shifting to:
· The north side at 1st, 2nd, and 4th Streets
Please slow down and follow signage through the construction
zone.
|
Project Overview
Detour Route & Vehicle Size Restrictions
REVISED VEHICLE SIZE RESTRICTIONS, STARTING JUNE 2, 2025
The following vehicle size restrictions will be in place starting June 2, 2025, for a period of three weeks.
|
Project Background
Highway 27 plays a key role in supporting the growth and development of several central Alberta communities. Within the Town of Sundre, Highway 27 is designated as an Over Sized Over Weight (OSOW) route and is a key contributor to Alberta’s High Load Corridor.
Alberta Transportation and Economic Corridors (TEC) has planned improvements to Highway 27 through the Town of Sundre, from the east boundary of the Town to the west boundary. The improvements are designed to support safer, more efficient travel through this area and enhance pedestrian safety.
The planned improvements include:
· Single lane roundabout at Highway 27/22/584/Range Road 54 (10th Street) intersection
· Permanent mini roundabouts at 2, 3 and 4 Street (West) intersections
· Intersection improvements at 1 Street (West) (right-in, right-out)
· Pavement rehabilitation, improvements to curbs, gutters, sidewalks, access management and lighting.
Following public engagement in 2022, additional improvements were identified including intersection upgrades at Centre Street, the Red Deer River bridge approach slabs, signalization of Highway 760 intersection, waterline relocations and additional lighting improvements.
The temporary mini roundabouts installed as a pilot project in 2017 have been assessed and deemed effective in improving both traffic flow as well as pedestrian safety. As such, TEC have directed the installation of permanent roundabouts along Highway 27 at 2 Street, 3 Street and 4 Street in 2024.
The anticipated timeline for the TEC improvements to Highway 27 is as follows:
- 2025 (January to February) - Miscellaneous construction activities (e.g. utility relocation, clearing of construction laydown area – in the northeast quadrant of Hwy 27/22/584/10th Street Intersection
- 2025 (March to October) – Construction activities for Hwy 27 Improvements
- 2025 (November) – Hwy 27 Construction completion (contingent on weather)
For more information about the Highway 27 improvement project, visit Highway 27 Improvements (Sundre) | Alberta.ca
Contact Information
If you have questions about this year’s construction work, please contact hwy27@sundre.com.
If you are interested in receiving project updates, please fill out the form below: